This project will construct a 0.85-mile-long urban road on a new location by extending Crossing Way through the Staunton Crossing development site to Valley Center Drive. The proposed road will be three lanes wide, including a single through lane in each direction and a center turn lane. There will be a 10-foot shared use path along the roadway.
The project will also include a 100-space park-and-ride lot with charging facilities for electric cars, and a transit stop with a covered shelter.
The total estimated cost for this project is $8.7 million, including $840,000 for preliminary engineering, $0 for right of way and $7.9 million for construction.
This project received $6,807,589 in SMART SCALE funding from an application submitted by the City of Staunton.
Benefits
The project will provide a new connection between Route 250 (Richmond Avenue) and North Frontier Drive. It will also improve access to transportation options with the inclusion of a park-and-ride lot and a new transit facility.
Major Milestones
Project Location/Design Approval: Spring 2020
Right of Way: N/A
Construction advertisement: Fall 2021
Resources
David Robinson, P.E.
(540) 332-7758
UPC: 111048
State ID: U000-132-350
Federal ID: STP-5132(140)
Lat/Long: 38.136944, -79.035000
Locality: