In Design: Hunter Mill Road over Colvin Run Bridge Replacement in Fairfax County
Cost and schedule ►
Traffic alerts ►
Public outreach ►
Note: A virtual design public hearing was held Sept. 16, watch the video here. View more hearing-related information here.
This project will replace the weight-restricted (ten tons) one-lane Hunter Mill Road bridge over Colvin Run. The new bridge will have two lanes separated by a median/splitter island.
The project also includes:
- An improved trail crossing south of the bridge
- Landscaping in the median/splitter island
- Abutments for a new trail bridge over Colvin Run (Fairfax County will construct the trail bridge in the future)
The existing bridge, built in 1974, averages 8,500 vehicles a day.
Estimated Costs
Preliminary Engineering - $930,000
Construction - $4.6 million
Total: $5.5 million
This project is financed with state funding (including State of Good Repair funds used for bridges) and Fairfax County funding.
Benefits
The project aims to reduce congestion and improve operations and safety.
Major Milestones
Public Information Meeting - April 2018
Virtual Public Involvement - May/June 2020
Virtual Design Public Hearing - September 2020
Begin Construction - Spring 2021
Resources
Vicente Valeza, P.E.
Structure & Bridge
Andrew Beacher, P.E.
Preliminary Engineering
Other relevant links:
Project Plans - June 2020
Conceptual Bridge Replacement Study Report - October 2017
Major funding source: State of Good Repair
Phase: In Design
UPC: 110499, 110433
State ID: 0674-029-358, P101, B643
Federal ID: STP-BR09 (295)
Lat/Long: 38.965604, -77.309634
Locality:
Fairfax