Recently Completed: Route 635 (Tucker Swamp Rd.) Bridge Replacement Project
Cost and schedule ►
The Virginia Department of Transportation reopened Route 635 (Tucker Swamp Road) over the Norfolk Southern Railroad on April 30, 2019 following a successful bridge replacement project. Curtis Contracting completed the $2.7 million project one day ahead of schedule.
Construction began in February 2018, and the contract had a fixed completion date of May 1, 2019.
The construction site was located on Tucker Swamp Road between Route 460 (General Mahone Boulevard) and Route 622 (New Road) in Ivor.
Benefits
New bridge on Route 635 (Tucker Swamp Road) over the Norfolk Southern Railroad.
Resources
Contact Info:
Hampton Roads Communications
757-956-3031
Phase: Active Construction
UPC: 93078
Lat/Long: 36.884412, -76.861877
Locality:
Southampton
Page last modified: April 30, 2019